Projects

Date
Location of Work
Project Scope
2023LED street light upgrade of roadway lightingLED upgrade
2023Installation of LED lighting in the Match District on South Main Street
LED upgrade
2023Rebuilding of overhead facilities on Durling Drive
Rebuild 
2023Rebuilding of overhead facilities on Acme Road
Rebuild
2023

Rebuilding of overhead facilities of overhead facilities on Wilson, Archwood & Brook Roads

Rebuild
2023Rebuilding of underground facilities on Cherry Hill, Harmony, Stauffer, Northwoods Trail & Hollybrier
Rebuild
2023Installation of underground facilities for Mount Eaton Estates, Phase 1
New Construction
2023Installation of underground facilities for The Highlands of Sharon 
New Construction
2023Installation & interconnection of 10MW of diesel generation at the Industry Substation to be used for peak shaving during high load events; this is a collaboration project with AMP and the City of Wadsworth
Special Project
2023Removal of old poles at various locations around our systemMaintenance Work